Home / Portfolio / SOLAR CARPORT MODEL W, 743 KW, BUCHAREST, ROMANIA

SOLAR CARPORT MODEL W, 743 KW, BUCHAREST, ROMANIA

Location
Bucharest, Romania
Solar power plant capacity
743 kW
Number of PV modules
1,485
Type of foundations
Concrete
Customer
SIMTEL (project for IKEA brand)
Project status
In progress
Number of parking spaces
240
Carport model
Model W / L-type
Parking space width
2,500 mm
Snow load
2.0 kPa
Wind load
0.5 kPa
Object type
Commercial parking of the shopping complex
Challenges
The project involves implementing one of the largest carport solutions in PILLAR’s portfolio for a facility with intensive customer traffic and high requirements for safety and operational reliability.
Key challenges included:
SELECTION CRITERIA
FOR THE ENGINEERING SOLUTION
Compactness, compliance with EU and national standards, and reliability under increased loads.
Adopt the Engineering Solution
For this facility, Model W / L-type solar carports with steel load-bearing structures on concrete foundations were selected, which made it possible to:
The project was developed taking into account the parking layout, traffic flows, and international retail standards.

РЕАЛІЗОВАНІ РІШЕННЯ

Інженери PILLAR
розробили проєкт палійно-
гвинтового фундаменту

Який ідеально підходить

Конструкція:

For this facility, Model W / L-type solar carports with steel load-bearing structures on concrete foundations were selected, which made it possible to:

Тип паль:

Навантаження:

Особливості монтажу

Implementation Process
Designing

The technical assignment, parking master plan and transport flow scenarios were analyzed. The design of Model W carports is calculated taking into account the estimated climatic loads and requirements for public facilities. Prepared project documentation KMD.

The metal structures of carports were manufactured in accordance with the design documentation with anti-corrosion protection. A step-by-step delivery of structures and components to the construction site with synchronization with the work schedule of the retail facility was provided.

Steel structures of carpets were installed on prepared concrete foundations. The work is carried out in stages in compliance with project bindings, safety requirements and without complete blocking of parking.

Result
As a result, a large-scale engineering solution is being implemented for the commercial parking of an international retail brand with integrated solar generation and extended functionality:
That is why the client turned to PILLAR

Experience in implementing large-scale carport projects, engineering solutions according to EU standards, and reliable structures for facilities with intensive operation.

That is why the client turned to PILLAR

Experience in implementing large-scale carport projects, engineering solutions according to EU standards, and reliable structures for facilities with intensive operation.

10_310_6

Документація проекту

ВІДГУК КЛІЄНТА

PILLAR Implemented Solutions
Here are examples of completed projects that showcase our engineering approach and technical expertise.
Get a response
from our manager today!
All articles
Get a response
from our manager today!
Отримайте відповідь
від нашого менеджера сьогодні!