For the facility, a screw-pile foundation was chosen, which allowed for:
Engineering preparation and planning An engineering assessment of the site was performed, and a layout scheme for over 10,000 supports was developed.
Engineering the foundation system A screw-pile foundation project was prepared for an industrial SPP with unified joints.
Production of piles The production and logistics of 10,230 ground screws were ensured in accordance with the construction schedule.
Serial installation Installation was performed using a flow method with control of verticality, depth, and design elevations.
Handover for SPP installation The foundation system was handed over for the subsequent installation of metal structures and panels.
because a scalable foundation was required for a 12 MW SPP, featuring serial installation without concrete and with full quality control.
because a scalable foundation was required for a 12 MW SPP, featuring serial installation without concrete and with full quality control.