For the project, a screw pile foundation was chosen in combination with metal structures, which allowed:
Site Engineering Preparation An analysis of the site was carried out and a layout of the foundations was formed, taking into account the layout of the ground SPP and integration with metal structures.
Foundation System Design The project of pile-screw foundation was developed with accurate binding of supports to the bearing system of SPP, taking into account loads, wind and snow impacts.
Production of piles The production and preparation of 4,804 geo-groups in accordance with the design parameters and the schedule for the implementation of the object was ensured.
Serial installation Installation is performed by the flow method with control of verticality, depth and design marks, in full synchronization with the installation of SES metal structures, without concreting and technological pauses.
Handover for SPP installation The foundation system was transferred for continuous installation of steel structures and photovoltaic modules within the approved construction schedule.
because a fast and precise solution was needed for a large-scale PV plant with full integration of the foundation and metal structures.
because a fast and precise solution was needed for a large-scale PV plant with full integration of the foundation and metal structures.