A pile‑screw foundation system was chosen for the project, which allowed for:
Site engineering preparation An analysis of the geological and layout conditions and constraints of the industrial site was carried out.
Foundation system design An individual design solution was developed, taking into account the site layout and the parameters of the solar power plant.
Pile manufacturing The production of ground screw foundations and metal structures was carried out in accordance with the project documentation.
Serial installation The foundations and structures were installed with control over verticality, geometry, and project levels.
Handover for solar power plant installation The prepared structure was handed over for the subsequent installation of photovoltaic modules.
an individually designed foundation and metal structures were required for the 608 kW solar power plant, with full quality control.
an individually designed foundation and metal structures were required for the 608 kW solar power plant, with full quality control.