The screw-pile foundation was chosen for the facility, which allowed for:
Engineering site preparation An analysis of the site was performed, and a layout scheme for the industrial solar power plant foundations was generated.
Foundation system engineering A unified design of the screw-pile foundation was developed for serial installation.
Ground screw production The production and supply of 2,880 screw piles were ensured in accordance with the construction schedule.
Serial installation The installation was performed using the flow method with constant control of verticality, depth, and design elevations.
Handover for solar power plant installation The foundation system was handed over for the subsequent installation of metal structures and solar panels.
a scalable and precise foundation was required for the serial installation of the solar power plant without the use of concrete.
a scalable and precise foundation was required for the serial installation of the solar power plant without the use of concrete.