A screw pile foundation was chosen for the object, which allowed:
Engineering site assessment An assessment of the terrain and soil conditions was conducted, taking into account the water saturation of the site.
Project preparation A screw foundation solution was developed with reference to the geometry of the ground-mounted ses structure.
Production of piles A set of screw piles has been prepared according to the design parameters.
Delivery and installation Installation of 24 ground screws was completed in 1 day with control over verticality and support stability.
Completion and handover The finished foundation base has been handed over for the subsequent installation of the solar power plant.
as an engineering solution with fast installation, adaptation to the terrain, and stable performance on water-saturated soils was required.
as an engineering solution with fast installation, adaptation to the terrain, and stable performance on water-saturated soils was required.