A screw-pile foundation was chosen for the facility, which allowed for:
Engineering Site Assessment Site conditions and the solar panel layout scheme were analyzed.
Project Preparation The screw-pile foundation project was developed with a direct reference to the SPP layout plan.
Pile Manufacturing A set of ground screws was prepared in accordance with the project parameters.
Delivery and Installation The installation of 52 ground screws was completed in 4 working days with strict control of verticality and height elevations.
Completion and Handover The finished foundation base was handed over for the installation of the solar power plant.
because a rapid and precise foundation installation was required—one that eliminated concrete and fit perfectly within the agreed SPP schedule.
because a rapid and precise foundation installation was required—one that eliminated concrete and fit perfectly within the agreed SPP schedule.