A pile-screw foundation was used for the facility, which allowed for:
Engineering site preparation Site analysis and development of the foundation layout for an industrial solar power plant.
Foundation system design Development of a unified design for serial installation.
Manufacturing of ground screws Manufacturing and supply of 8,164 screw piles according to the schedule.
Serial installation Flow-based installation with control of verticality, depth, and design elevations.
Handover for solar power plant installation Readiness of the foundation system for the installation of metal structures and panels.
as a scalable screw foundation was required for the serial installation of the solar power plant without concrete.