A screw-pile foundation was chosen for the facility, which allowed for:
Engineering Site Assessment An analysis of the site conditions and the solar panel layout planning was conducted.
Project Preparation A screw-pile foundation project was developed with a direct reference to the layout scheme for 84 panels.
Manufacturing of Piles A set of ground screws was prepared in accordance with the project specifications.
Delivery and Installation The installation of 36 ground screws was completed in 2 working days with strict control of verticality and height elevations.
Completion and Handover The finished foundation base was handed over for the subsequent installation of the solar power plant.
because they required a rapid and precise foundation installation that could fit into the rigid SPP assembly schedule.
because they required a rapid and precise foundation installation that could fit into the rigid SPP assembly schedule.