Home / Portfolio / CONSTRUCTION OF A PIER ON THE KHADZHYBEY ESTUARY

CONSTRUCTION OF A PIER ON THE KHADZHYBEY ESTUARY

Location
Odesa, Khadzhybey Estuary
Date
April 2018
Terms:
3 working days
Ground screws
14 pcs
Object type
Pier (hydrotechnical structure)
Challenges
The implementation of the project involved several technical constraints related to the site conditions:
SELECTION CRITERIA
FOR THE ENGINEERING SOLUTION
The key factors were the rapid construction of the pier and the reliable performance of the foundation in limestone soil.
Adopted Engineering Solution
The optimal solution was a ground screw foundation, which allowed to:
The foundation was designed taking into account the hydrological conditions and the loads from the pier structure.
РЕАЛІЗОВАНІ РІШЕННЯ
Інженери PILLAR
розробили проєкт палійно-
гвинтового фундаменту
Який ідеально підходить

Конструкція:

The optimal solution was a ground screw foundation, which allowed to:

Тип паль:

Навантаження:

Особливості монтажу
Implementation Process
Design

Development of the layout for 14 ground screws, taking into account the geology and the configuration of the pier.

Preparation of ground screws according to the design parameters.

Rapid installation of supports with control over screw depth and geometry.

Result
Thanks to the use of a ground screw foundation:
That is why the client turned to PILLAR

because they required the rapid construction of a pier with reliable fixation in limestone soil without the use of concrete.

That is why the client turned to PILLAR

because they required the rapid construction of a pier with reliable fixation in limestone soil without the use of concrete.

photo_2018-04-14_17-3photo_2018-04-14_17-2
Документація проекту
ВІДГУК КЛІЄНТА
PILLAR Implemented Solutions
Here are examples of completed projects that demonstrate our engineering approach and technical expertise.