A screw-pile foundation was chosen for the project, which made it possible to:
Site Engineering Assessment An analysis of the terrain, soil moisture levels, and the location of existing structures was conducted.
Project Preparation A screw-pile foundation design was developed, aligned with the site’s elevation changes and the geometry of the buildings.
Pile Fabrication A set of screw piles was prepared according to the design specifications.
Delivery and Installation The installation of 9 ground screws was completed in 1 day, with careful monitoring of vertical alignment and elevations.
Completion and Handover The completed foundation base was handed over for the subsequent construction of the fishing house and gazebo.
as an engineering solution was required for rapid installation on sloped terrain in water-saturated soils.