A screw pile foundation was selected for the project, which allowed:
Engineering site assessment The assessment of filled soils and planning conditions has been conducted with reference to the dome geometry of the building.
Project preparation The screw pile foundation project was developed with a radial layout of supports and load calculations.
Production of piles A set of screw piles has been prepared according to the design quantity and test results.
Delivery and installation The installation of 110 ground screws was performed with control over verticality, geometry, and compliance with design parameters.
Completion and handover The finished foundation base has been handed over for the subsequent construction of the dome house.
as an engineering solution was required for the stable performance of residential houses in water-saturated soils.