A screw-pile foundation was selected for the project, which made it possible to:
Site Engineering Assessment An analysis was carried out to evaluate the development conditions, equipment accessibility, and the placement of existing structures.
Project Preparation A screw-pile foundation design was developed with precise alignment to the architectural layout of each building.
Pile Fabrication A set of screw piles was prepared in accordance with the design quantity and calculated specifications.
Delivery and Installation The installation of 142 screw piles was carried out in stages, with careful monitoring of vertical alignment and adherence to the design elevations.
Completion and Handover The completed foundation bases were handed over for the subsequent construction of the guest houses.
as an engineering solution was required to build within an existing development while precisely implementing the project design.
as an engineering solution was required to build within an existing development while precisely implementing the project design.