For the crane runway, a ground screw foundation was chosen, which made it possible to:
Design Development of the layout for 152 ground screws, taking into account the loads and the configuration of the crane runway.
Production Manufacturing of ground screws according to the design parameters.
Installation Precise installation of supports within an operating workshop with verticality and elevation mark control.
because they required foundation installation in an operating workshop without concrete, contamination, and with minimal production downtime.
because they required foundation installation in an operating workshop without concrete, contamination, and with minimal production downtime.