GROUND SCREW FOUNDATION FOR A HANGAR IN KYIV

Location
Kyiv
Date
January 2012
Terms:
6 working days
Ground screws
100 pcs
Object type
Industrial hangar
Challenges
The foundation was implemented under challenging conditions:
SELECTION CRITERIA
FOR THE ENGINEERING SOLUTION
The decisive factors were the possibility of winter installation, ease of setup, and the absence of concrete work.
Adopted Engineering Solution
For the project, a ground screw foundation was chosen, which made it possible to:
The foundation was designed taking into account the loads from the metal hangar structure.
РЕАЛІЗОВАНІ РІШЕННЯ
Інженери PILLAR
розробили проєкт палійно-
гвинтового фундаменту
Який ідеально підходить

Конструкція:

For the project, a ground screw foundation was chosen, which made it possible to:

Тип паль:

Навантаження:

Особливості монтажу
Implementation Process
Production

Preparation of 100 ground screws according to the design parameters.

Rapid installation of supports with depth and verticality control, forming a level foundation plane.

Result
As a result of the project:
That is why the client turned to PILLAR

because they required the rapid construction of a hangar foundation in winter without concrete work or technological pauses.

That is why the client turned to PILLAR

because they required the rapid construction of a hangar foundation in winter without concrete work or technological pauses.

DSC09839DSC09795 (1)
Документація проекту
ВІДГУК КЛІЄНТА
PILLAR Implemented Solutions
Here are examples of completed projects that demonstrate our engineering approach and technical expertise.
Get a response
from our manager today!
All articles
Get a response
from our manager today!
Отримайте відповідь
від нашого менеджера сьогодні!