FOUNDATION FOR AN OVERPASS AT A GAS PROCESSING PLANT

Location
Merefa, Kharkiv region
Date
December 2021
Terms:
3 working days
Ground screws
94 pcs
Object type
Overpass (industrial facility)
Challenges
The foundation implementation was carried out within an industrial enterprise with increased requirements for deadlines and structural reliability, which involved:
SELECTION CRITERIA
FOR THE ENGINEERING SOLUTION
Execution deadlines, performance in sandy soils, and reliability requirements for the industrial overpass foundation.
Adopted Engineering Solution
A screw pile foundation was chosen for the facility, which allowed:
The foundation project was developed taking into account the loads from the metal overpass, the operating conditions of the industrial facility, and the requirements for the accuracy of support positioning.
РЕАЛІЗОВАНІ РІШЕННЯ
Інженери PILLAR
розробили проєкт палійно-
гвинтового фундаменту
Який ідеально підходить

Конструкція:

A screw pile foundation was chosen for the facility, which allowed:

Тип паль:

Навантаження:

Особливості монтажу
Implementation Process
Engineering site assessment

An assessment of the soil conditions and foundation placement within the production area of the enterprise was conducted.

A screw foundation project was developed taking into account the loads from the overpass structure and the specified execution deadlines.

A set of screw piles has been prepared according to the design quantity and calculated parameters.

The installation of 94 ground screws was performed in sandy soil with verticality and stability control for the supports.

The finished foundation base has been handed over for the subsequent installation of the metal overpass.

Result
The use of a screw foundation allowed for the implementation of the project within tight deadlines and provided a reliable base for the industrial structure:
That is why the client turned to PILLAR

as an engineering solution with fast installation and predictable reliability for the industrial overpass was required.

That is why the client turned to PILLAR

as an engineering solution with fast installation and predictable reliability for the industrial overpass was required.

DSC_0872DSC_0893
Документація проекту
ВІДГУК КЛІЄНТА
PILLAR Implemented Solutions
Here are examples of completed projects that demonstrate our engineering approach and technical expertise.
Get a response
from our manager today!
All articles
Get a response
from our manager today!
Отримайте відповідь
від нашого менеджера сьогодні!