A pile-screw foundation was chosen for the project, which allowed to:
Engineering Assessment of the Site An analysis of the subsiding soils and site accessibility conditions was carried out.
Project Preparation A pile-screw foundation design was developed, aligned with the geometry of the modular house.
Pile Production A set of ground screws was prepared in accordance with the project specifications.
Delivery and Installation Thirty-nine ground screws were installed in 2 working days with strict control of vertical alignment and design elevations.
Completion and Handover The completed foundation was handed over for the installation of the modular house.
they required an engineering solution for fast installation of a modular house on subsiding soils.
they required an engineering solution for fast installation of a modular house on subsiding soils.